Capital Stewardship Phase I and II as of 1/1/07:
Total Pledged: $1,992,208
Total Received: $1,599,166
Other (cash, offerings, gifts,
memorials, bequests): $ 659,556

Total Receipts: $2,258,722

 

Phase I Building Progress:

9/29/03 Mortgage Commitment received from Shore Community Bank for $3,000,000.
5/1/05 Actual construction begun - area cleared for Sunday School addition and the Choir Wing addition.
9/12/05 WNS opens Fall 2005 Semester in new decorated classrooms!
Work is underway for the Music Ministry Wing as well - concrete has been poured - builder anticipates breaking through Sanctuary wall by mid-September - anticipated completion dates will be announced later in the year as progress is monitored more closely.
The bidding process for the House of Hope project has begun.
10/1/05 Demolition completed on the Music Ministry Wing.
Roofing completed week of 10/4/05.
10/5/05 New duct work for offices & classrooms completed.
Grand opening of the SonRise Campaign construction was held during April 28-30, 2006.
Final planning for the House of Hope is underway. Plans are approved and out for bid.